Subdivisions/Site Plans (Public Hearing not Required)

Case #SB-08-2019: CCBC Properties, LLC, Owner/Applicant

Property Description/Location: Tax Map 83A-1-1; 83A-1-1B; 83A-1-2; 83A-1-2A; Property is located in Carmel Church Business Centre at the intersection of Rogers Clark Boulevard & Enterprise Parkway, Mattaponi Voting District.

Zoning: The property is zoned M-1 Industrial

Action: Applicant is seeking Preliminary Plat Approval to create eighteen (18) lots.

Required Approvals: Planning Commission approval of the subdivision plat is required – the case is tentatively scheduled for the February 2020 Planning Commission Meeting.


Case #SB-07-2019: Brookwood Development, Owner/Applicant

Property Description/Location: Tax Map 56-A-140; Property is to the northwest of Brookwood Section 1, Mattaponi Voting District.

Zoning: The property is zoned R-1

Action: Applicant is seeking Final Plat Approval to create Section 2 of Brookwood consisting of 50 lots.

Required Approvals: Planning Commission approval of the final plat of subdivision is required – the case is scheduled for the January 23, 2020 Planning Commission Meeting.


Case #SB-06-2019: John & Billie Bordeaux (Villeboro Acres), Owner/Applicant

Property Description/Location: Tax Map 17-A-71B; Property is located on Villeboro Road, approx. 0.4 miles west of Fredericksburg Turnpike, Port Royal Voting District.

Zoning: The property is zoned Rural Preservations

Action: Applicant is seeking Preliminary/Final Plat Approval to create four (4) ten acre residential building lots.

Required Approvals: Planning Commission approval of the subdivision plat is required – the case is tentatively scheduled for the January 2020 Planning Commission Meeting.


Case: SP-11-2019: Accuracy International Tube Range; Accuracy International of North America, Inc., Owner/Applicant

Property Description/Location: Tax Map #52-A-138 and 52-A-139; 16342 Edwards Road, Mattaponi Voting District

Zoning: M-1 Industrial

Action: The Applicant has submitted for approval a site plan for a testing facility (underground firing range). This replaces a previously approved site plan that included a warehouse and testing facility


Case #SB-04-2019: Rogers-Chenault, Inc., Owner/Applicant

Tax Map 52-A-55; 52-A-56; 52-A-57

Property is located at 7092 Durrette Road, west of Jefferson Davis Highway, abutting the YMCA, Madison Voting District.

Property is zoned Planned Residential Development per RZ-04-2018, approved January 2019.

Applicant is seeking Preliminary Plat Approval to create 71 residential building lots in the Maple Grove development, an active adult community.

Planning Commission Approval is required – the case is scheduled for the January 23, 2020 Planning Commission Meeting.


Case SP-10-2019: Early Grading Plan for Airlee (Caroline Industrial Center)

East side of Route 1 across from CCC Road

Airlee Development, LLC, Owner/Applicant

Tax Map #67-3-1; 67-3-2; 68-1-2; Mattaponi Voting District.

The Applicant has submitted an early grading plan for review & approval to comply

with the proffers associated with RZ-02-2017 (approved by the Board of Supervisors in

April 2018).


Case SP-05-2019: Verizon Wireless – Lake Caroline Cell Tower

Tax Map #67-3-4B, 19443 Jefferson Davis Highway (Vision Baptist Church)

Mattaponi Voting District.

The Applicant has submitted for approval, the site plan for a 190’ monopole cell tower

and associated ground mounted equipment. The Board of Supervisors granted a special

exception permit to Verizon Wireless for the tower at the March 12, 2019 meeting.


Case SP-04-2019: Maple Grove Subdivision

Tax Map #52-A-55, 56 & 57; 7092 Durrette Road, abutting the YMCA

Madison Voting District.

The Applicant has submitted for approval construction plans for the site development

of 19.9 acres for a 72 lot Active Adult Community. The Board of Supervisors approved

rezoning the property to Planned Residential Development at the January 22, 2019

meeting (RZ-04-2018 – Durrette Subdivision).

A preliminary plat must be approved by the Planning Commission prior to issuance of a

land disturbance permit for site work. To date, a preliminary plat has not been

submitted.


Case SP-02-2019: Verizon Wireless – Lake Land’or Cell Tower

Tax Map #51-A60A (part); 5259 Ladysmith Road

The Applicant has submitted for approval, the site plan for a 190’ monopole cell tower

and associated ground mounted equipment. The Board of Supervisors granted a special

exception permit to Verizon Wireless for the tower at the January 8, 2019 meeting.



Case #SB-01-2019, Pendleton - Tricord, Inc. Applicant

Tax Map 52-A-80; 80C; 80D; 80E; 80F; 355 Acres total – 97 acres to be developed.

This site abuts the existing Pendleton Development on the west (continuation of Edmund

Pendleton Drive.)

Zoning was approved in December, 2000 for Planned Mixed Use Development for 3,508

units of which 180 lots have been platted to date; 174 units constructed/under

construction to date.

Applicant is seeking Preliminary Plat Approval for 704 lots to include 318 Townhouse Lots

& 386 Single Family Dwelling Lots.


Case #SP-04-2018, M.C. Dean, Applicant

Tax Map 83-A-75, 146 acres +/-,  Northeast corner of Coleman’s Mill and Dry Bridge Road.

Site Plan approval for an Access Road off Route 684, Dry Bridge Road

Land Disturbance Permit has been issued, and site work has commenced.


Case #SP-07-2018 Newcomb Refrigeration, Applicant

Tax Map 108-A-42A, 1.38 Acres +/-,  31336 Richmond Turnpike, Doswell, VA  23047 (Dawn), M-1 Industrial Zoning

Site Plan review (approval pending) for a 4,383 square foot office/warehouse.